i have been asked to swap over 19 lamp units in a stair well.... i would say it is like for like, and wanted to know what sort of price you would ask for..

there are 19 of these energy saving bulkhead fittings. i may need to adapt the fixing type..

many thanks..

Link to comment
Share on other sites

13 answers to this question

Recommended Posts

i have been asked to swap over 19 lamp units in a stair well.... i would say it is like for like, and wanted to know what sort of price you would ask for..

there are 19 of these energy saving bulkhead fittings. i may need to adapt the fixing type..

many thanks..

Allowing 30mins each, (which may be a bit modest)

i.e.

find lamp position & fuse to isolate,

carry tools to lamp,

up ladder,

verify dead.. safe isolation etc..

remove old

fit new

re energise & test ok...

shift ladder & tools to next position..

ect... repeat 18 more times...

(have a tea break.. visit loo!)

19 x 30mins = 9.5hours straight work IMHO

Stairwell???!!

any tricky ladder bits?

realistically more like 1.5 days at a guess

:|;)

Link to comment
Share on other sites

Need more info mate - lighting type (em/std), wiring type, type of fitting, ease of access etc.

KME

Link to comment
Share on other sites

wiring system is steel conduit, lamp is a circular bulk head, access is easy - small ladder jobby,

cable type will be singles, so may need to be extended using cable crimps...

Link to comment
Share on other sites

do the light sit on the conduit? or are they top entry or something like that?

I could be wrong here but i would be looking to see of any of them had been wired through. Will add time and a few more connections, but not much.

is this not just a days work + mats?

Link to comment
Share on other sites

what is meant by '2d'?

Link to comment
Share on other sites

the units are 2d

Link to comment
Share on other sites

If its conduit boxes even if you have got to lenghten cables it should be straight forward. Get a price for fittings work out how long it should take you should be able to price from that. Personallty I would allow a days work as you don't want anything less else its not worth doing job.

Batty

Link to comment
Share on other sites

the person how wants it done said that he think i should get about 5-6 done a day...

Link to comment
Share on other sites

the person how wants it done said that he think i should get about 5-6 done a day...

Go for three days plus materials then, personally sounds to me like a days work but without seeing job I am probably way out.

Link to comment
Share on other sites

the person how wants it done said that he think i should get about 5-6 done a day...

price for that then, if thats what they think they should be expecting a quote for three days work. are you the only one quoting? are they happy with the stairwell being closed three days?

Link to comment
Share on other sites

it will have to be split over a couple of weeks, as the building is only closed on mondays..

Link to comment
Share on other sites

Archived

This topic is now archived and is closed to further replies.

×
×
  • Create New...

Important Information

Terms of UseWe have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.