Yes 400v
yes winding out then back and powering back up he calls this training
it horrifies me that he could injure some one with his inept attitude
i see lol arc auto correct lol
he insists he is carrying out training.
we go in to the LV sub station and he has us opening a live breaker racking it out then back in them closing it. I asked where the Schneider manuals are so that i can have a read over them to get more familiar with their internal workings.
during this...
Hi i am looking for some advice, I have recently started working at a Biomass Power plant. The SAP on site dost fill me with confidence the whole site is new with all new Schneider switch gear. He has us racking in and out live breakers and opening and closing them, 1 with no theory behind it 2...