OV-G confirmation
JavaScript is disabled. For a better experience, please enable JavaScript in your browser before proceeding.
You are using an out of date browser. It may not display this or other websites correctly.
You should upgrade or use an
alternative browser
.
Reply to thread
Help Support Talk Electrician Forum:
This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.
Message
<blockquote data-quote="binky" data-source="post: 494161" data-attributes="member: 490"><p>un-bury the DC cable - it will last about 5 ears buried, it needs armouring or alternative cable route.</p><p></p><p>Wouldn't worry too much about the G59 settings it doesn't really affect how it works, although strictly incorrect to regs. If your inverter is 3.6kW, ie 16A limited then it falls under the G83 (98) domestic settings which makes getting DNO approval automatic. If you go over 16A max output from the inverter, then DNO is suppossed to be notified for approval before installation. THe DNO can refuse connection and insist you turn the system off if over 16A without their permission..</p><p></p><p>Give them sh!t missus :slap</p></blockquote><p></p>
[QUOTE="binky, post: 494161, member: 490"] un-bury the DC cable - it will last about 5 ears buried, it needs armouring or alternative cable route. Wouldn't worry too much about the G59 settings it doesn't really affect how it works, although strictly incorrect to regs. If your inverter is 3.6kW, ie 16A limited then it falls under the G83 (98) domestic settings which makes getting DNO approval automatic. If you go over 16A max output from the inverter, then DNO is suppossed to be notified for approval before installation. THe DNO can refuse connection and insist you turn the system off if over 16A without their permission.. Give them sh!t missus :slap [/QUOTE]
Insert quotes…
Verification
Post reply
Green Renewable Energy Forum
Solar PV Forum
OV-G confirmation