Hello all
Went to look at a job today (finally!). Client just wants 2 bathroom spots relocated (and new fittings provided) and an external light fitted.
I'm ok with what needs doing and the fact that they're notifiable works. I'm not sure about what I'm obliged to do...
She's got an old re-wireable fuseboard on a PME system. I saw NO sign of an RCD anywhere. Bonding was in place to gas and water, although gas was only 6mm.
She said she'd had the shower replaced last year, but that no wiring was done - it was just a straight swap.
I thought there might be an RCD to cover the shower cct in the loft space above - then I put my brain back in and thought that that would be the most ridiculous place to have one Blushing.
Just need some guidance (again) on anything compulsory I'd need to do before the required work and anything else I should have looked at/for.
BTW, I was going to run the external fitting from an fcu on the downstairs ring.
Thank you.
Went to look at a job today (finally!). Client just wants 2 bathroom spots relocated (and new fittings provided) and an external light fitted.
I'm ok with what needs doing and the fact that they're notifiable works. I'm not sure about what I'm obliged to do...
She's got an old re-wireable fuseboard on a PME system. I saw NO sign of an RCD anywhere. Bonding was in place to gas and water, although gas was only 6mm.
She said she'd had the shower replaced last year, but that no wiring was done - it was just a straight swap.
I thought there might be an RCD to cover the shower cct in the loft space above - then I put my brain back in and thought that that would be the most ridiculous place to have one Blushing.
Just need some guidance (again) on anything compulsory I'd need to do before the required work and anything else I should have looked at/for.
BTW, I was going to run the external fitting from an fcu on the downstairs ring.
Thank you.