Been meaning to post this for a while but keep forgetting.
When filling out a PVT DC cert, under the Array Parameters we have Voc and Isc to fill out.
Been on 2 big contracts with contradicting requirements.
One says to put in the parameters of ONE panel, so for example 10 x 255 panels would still be Voc - 37.4 and Isc - 8.98
The other say to multiply the Voc by the number of panels. So the same example would be Voc - 374 and Isc still 8.98.
So, which, if either is correct?
Thanks